Road Resurfacing: 12th Avenue, Baldwin Street to Port Sheldon Street, Georgetown Township

WHEN: Beginning the week of Oct. 12

WHERE:12th Avenue, Baldwin Street to Port Sheldon Street, Georgetown Township

WHY: Road resurfacing

BACKGROUND: Beginning the week of Oct. 12, contractors for the Ottawa County Road Commission are tentatively expected to begin work on a resurfacing project on 12th Avenue between Baldwin Street and Port Sheldon Street in Georgetown Township.

Work on this project is expected to last through late October/early November; however, please note that all work is weather-dependent, and completion dates are subject to change.

TRAFFIC IMPACT: Traffic will be maintained using temporary lane closures under flag control. Be prepared for possible delays when traveling through this area while work is taking place.

Road Closure: 172nd Avenue, Comstock Street to Hayes Street, Grand Haven Township

WHAT: Permitted road closure

WHEN: Beginning Oct. 12

WHERE: 172nd Avenue, Comstock Street to Hayes Street, Grand Haven Township

WHY: Permitted sanitary/storm sewer work

BACKGROUND: 172nd Avenue between Comstock Street and Hayes Street in Grand Haven Township will be closed beginning Monday, Oct. 12, for permitted sanitary and storm sewer work.

This work is scheduled to last through Oct. 23. All dates are tentative and work is weather-dependent.

TRAFFIC IMPACT: A detour route will consist of Comstock Street to 168th Avenue to Hayes Street.

Road Closure: North 144th Avenue, Butternut Drive to Quincy Street, Holland Township

WHAT: Permitted road closure

WHEN: Beginning Oct. 12

WHERE: North 144th Avenue, Butternut Drive to Quincy Street, Holland Township

WHY: Permitted water main/sanitary sewer work

BACKGROUND: North 144th Avenue between Butternut Drive and Quincy Street in Holland Township will be closed beginning Monday, Oct. 12, for permitted water main and sanitary sewer work.

This work is scheduled to last through Oct. 23. All dates are tentative and work is weather-dependent.

TRAFFIC IMPACT: A detour route will consist of Butternut Drive to Quincy Street.

Current Projects & Closures

TOWNSHIP

ROAD

SEGMENT

WORK

DATES

AUTHORITY

TRAFFIC

Georgetown

12th Ave.

Port Sheldon St. to Baldwin St.

Resurfacing

Oct. 12-Nov.

OCRC

Lane Closures

Holland

N. 144th Ave.

Butternut Dr. to Quincy St.

Water Main/Sanitary Sewer

Oct. 12-23

Permit

Road Closed

Grand Haven

172nd Ave.

Comstock St. to Hayes St.

Sanitary/Storm Sewer

Oct. 12-23

Permit

Road Closed

Blendon

Baldwin St.

56th Ave. to 48th Ave.

Resurfacing

Oct. 5-17

OCRC

Road Closed

Georgetown/
Jamestown

New Holland St.

Chicago Dr. to Hudsonville City Limits

Resurfacing

Oct. 2-23

OCRC

Lane Closures

Georgetown

Baldwin St.

20th Ave. to Cottonwood Dr.

Resurfacing

Sept. 28-Oct. 30

OCRC

Lane Closures

Holland

Beeline/Greenly St.

Riley St. to 120th Ave.

Resurfacing

Sept. 28-Oct. 16

OCRC

Lane Closures

Holland

James St.

At 120th Ave.

Sanitary Sewer

Sept. 21-Nov. 30

Permit 

Road Closed

Port Sheldon

164th Ave.

Butternut Dr. to New Holland St.

Water Main

Aug. 10-Nov. 30

Permit

Road Closed

Blendon/
Georgetown

48th Ave.

At Baldwin St.

Roundabout

July 27-Oct. 17

OCRC

Road Closed

Holland

104th Ave.

James St. to Felch St.

Bridge Rehab

July 6-Nov. 30

OCRC

Road Closed

Allendale

60th Ave

Lincoln St. to Comfort Dr.

Water Main

June 3-Oct. 30

Permit

Road Closed

Holland

120th Ave.

James St. to Lakewood Blvd.

Sanitary Sewer

May 4-Nov. 30

Permit

Road Closed

Georgetown

48th Ave.

Port Sheldon St. to Bauer Rd.

Water Main

March 30-Nov. 30

Permit

Road Closed

Olive

Van Buren St.

U.S. 31 to 120th Ave.

Water Main

Nov. 3-Nov. 30

Permit

Road Closed

Port Sheldon

Van Buren St.

Butternut Dr. to U.S. 31

Water Main

Sept. 4-Nov. 30

Permit

Road Closed

Subdivision Resurfacing Schedule

TOWNSHIP

DATES

Crockery

Beginning October 12

Jamestown

TBD

Park

Beginning August 24

Information about Township subdivision resurfacing projects can be found on the Township Subdivision Resurfacing project website. 

— All dates listed in the above tables are estimates and are subject to change without notice. Always obey all work zone and road closure signs and be sure to follow all posted detours.

ONN Staff profile image
by ONN Staff

Subscribe to Our Newsletter for Daily or Weekly Updates

Customize your email newsletter subscription for daily or weekly updates on your favorite topics.

Success! Now Check Your Email

To complete Subscribe, click the confirmation link in your inbox. If it doesn’t arrive within 3 minutes, check your spam folder.

Ok, Thanks

Read More