Weekly Construction Update: Oct. 12
Road Resurfacing: 12th Avenue, Baldwin Street to Port Sheldon Street, Georgetown Township
WHEN: Beginning the week of Oct. 12
WHERE:12th Avenue, Baldwin Street to Port Sheldon Street, Georgetown Township
WHY: Road resurfacing
BACKGROUND: Beginning the week of Oct. 12, contractors for the Ottawa County Road Commission are tentatively expected to begin work on a resurfacing project on 12th Avenue between Baldwin Street and Port Sheldon Street in Georgetown Township.
Work on this project is expected to last through late October/early November; however, please note that all work is weather-dependent, and completion dates are subject to change.
TRAFFIC IMPACT: Traffic will be maintained using temporary lane closures under flag control. Be prepared for possible delays when traveling through this area while work is taking place.
Road Closure: 172nd Avenue, Comstock Street to Hayes Street, Grand Haven Township
WHAT: Permitted road closure
WHEN: Beginning Oct. 12
WHERE: 172nd Avenue, Comstock Street to Hayes Street, Grand Haven Township
WHY: Permitted sanitary/storm sewer work
BACKGROUND: 172nd Avenue between Comstock Street and Hayes Street in Grand Haven Township will be closed beginning Monday, Oct. 12, for permitted sanitary and storm sewer work.
This work is scheduled to last through Oct. 23. All dates are tentative and work is weather-dependent.
TRAFFIC IMPACT: A detour route will consist of Comstock Street to 168th Avenue to Hayes Street.
Road Closure: North 144th Avenue, Butternut Drive to Quincy Street, Holland Township
WHAT: Permitted road closure
WHEN: Beginning Oct. 12
WHERE: North 144th Avenue, Butternut Drive to Quincy Street, Holland Township
WHY: Permitted water main/sanitary sewer work
BACKGROUND: North 144th Avenue between Butternut Drive and Quincy Street in Holland Township will be closed beginning Monday, Oct. 12, for permitted water main and sanitary sewer work.
This work is scheduled to last through Oct. 23. All dates are tentative and work is weather-dependent.
TRAFFIC IMPACT: A detour route will consist of Butternut Drive to Quincy Street.
Current Projects & Closures
TOWNSHIP | ROAD | SEGMENT | WORK | DATES | AUTHORITY | TRAFFIC |
Georgetown | 12th Ave. | Port Sheldon St. to Baldwin St. | Resurfacing | Oct. 12-Nov. | OCRC | Lane Closures |
Holland | N. 144th Ave. | Butternut Dr. to Quincy St. | Water Main/Sanitary Sewer | Oct. 12-23 | Permit | Road Closed |
Grand Haven | 172nd Ave. | Comstock St. to Hayes St. | Sanitary/Storm Sewer | Oct. 12-23 | Permit | Road Closed |
Blendon | Baldwin St. | 56th Ave. to 48th Ave. | Resurfacing | Oct. 5-17 | OCRC | Road Closed |
Georgetown/ | New Holland St. | Chicago Dr. to Hudsonville City Limits | Resurfacing | Oct. 2-23 | OCRC | Lane Closures |
Georgetown | Baldwin St. | 20th Ave. to Cottonwood Dr. | Resurfacing | Sept. 28-Oct. 30 | OCRC | Lane Closures |
Holland | Beeline/Greenly St. | Riley St. to 120th Ave. | Resurfacing | Sept. 28-Oct. 16 | OCRC | Lane Closures |
Holland | James St. | At 120th Ave. | Sanitary Sewer | Sept. 21-Nov. 30 | Permit | Road Closed |
Port Sheldon | 164th Ave. | Butternut Dr. to New Holland St. | Water Main | Aug. 10-Nov. 30 | Permit | Road Closed |
Blendon/ | 48th Ave. | At Baldwin St. | Roundabout | July 27-Oct. 17 | OCRC | Road Closed |
Holland | 104th Ave. | James St. to Felch St. | Bridge Rehab | July 6-Nov. 30 | OCRC | Road Closed |
Allendale | 60th Ave | Lincoln St. to Comfort Dr. | Water Main | June 3-Oct. 30 | Permit | Road Closed |
Holland | 120th Ave. | James St. to Lakewood Blvd. | Sanitary Sewer | May 4-Nov. 30 | Permit | Road Closed |
Georgetown | 48th Ave. | Port Sheldon St. to Bauer Rd. | Water Main | March 30-Nov. 30 | Permit | Road Closed |
Olive | Van Buren St. | U.S. 31 to 120th Ave. | Water Main | Nov. 3-Nov. 30 | Permit | Road Closed |
Port Sheldon | Van Buren St. | Butternut Dr. to U.S. 31 | Water Main | Sept. 4-Nov. 30 | Permit | Road Closed |
Subdivision Resurfacing Schedule
TOWNSHIP | DATES |
Crockery | Beginning October 12 |
Jamestown | TBD |
Park | Beginning August 24 |
Information about Township subdivision resurfacing projects can be found on the Township Subdivision Resurfacing project website.
— All dates listed in the above tables are estimates and are subject to change without notice. Always obey all work zone and road closure signs and be sure to follow all posted detours.