Weekly Construction Update: Oct. 26
Photo by Zac Gudakov / Unsplash

Weekly Construction Update: Oct. 26

ONN Staff profile image
by ONN Staff

112th Avenue

Port Sheldon Street to New Holland Street (Olive)

A full closure of 112th Avenue between Port Sheldon Street and New Holland Street is scheduled to begin Thursday, Oct. 29, for water main work.

Scheduled start: Oct. 29

Anticipated completion: Nov. 20

96th Avenue

South of Stanton Street (Blendon/Olive)

Full closure scheduled for culvert replacement work.

Scheduled start: Oct. 28

Anticipated completion: Nov. 2

Current road closures

Van Buren Street

Butternut Drive to U.S. 31 (Port Sheldon/Olive)

Full closure for water main work.

Anticipated reopening: Nov. 30

Van Buren Street

U.S. 31 to 120th Avenue (Port Sheldon/Olive)

Full closure for water main work.

Anticipated reopening: Nov. 30

120th Ave.

Lakewood Boulevard to James Street (Holland)

Full closure for sanitary sewer work.

Anticipated reopening: Nov. 30

60th Avenue

Lincoln St. to Comfort Drive (Allendale)

Full closure for water main work.

Anticipated reopening: Oct. 30

104th Avenue

James Street to Riley Street (Holland)

Full closure for bridge rehabilitation work.

Anticipated reopening: Nov. 30

164th Avenue

Butternut Drive to New Holland Street (Port Sheldon)

Full closure for water main work.

Anticipated reopening: Nov. 30

James Street

At 120th Avenue (Holland)

Full closure for sanitary sewer work.

Anticipated reopening: Nov. 30

172nd Avenue

Comstock Street to Hayes Street (Grand Haven)

Full closure for sanitary/storm sewer work.

Anticipated reopening: Oct. 30

Butternut Drive

At Van Buren Street (Port Sheldon)

Full closure for water main work.

Anticipated reopening: Nov. 13

Other construction activity

12th Avenue

Port Sheldon Street to Baldwin Street (Georgetown)

Resurfacing work. Motorists should expect lane restrictions.

Anticipated completion: Nov. 15

Taft Street

174th Avenue to 168th Avenue (Spring Lake)

Resurfacing work. Motorists should expect lane restrictions.

Anticipated completion: Oct. 30 

Subdivision Resurfacing Program

Township

Scheduled Start

Jamestown

Beginning Oct. 26

Port Sheldon

Beginning Oct. 26

Work zone reminder

Construction schedules are estimates and may change due to weather or other circumstances. Please obey posted road closure signs, follow designated detours, and use caution when traveling through work zones.

Questions about road work?

For questions about construction projects or traffic impacts, contact the Ottawa County Road Commission at 616-842-5400 or use its online contact form.

Information about Township subdivision resurfacing projects can be found on the Township Subdivision Resurfacing project website. 

— All dates listed in the above tables are estimates and are subject to change without notice. Always obey all work zone and road closure signs and be sure to follow all posted detours.

ONN Staff profile image
by ONN Staff

Subscribe to Our Newsletter for Daily or Weekly Updates

Customize your email newsletter subscription for daily or weekly updates on your favorite topics.

Success! Now Check Your Email

To complete Subscribe, click the confirmation link in your inbox. If it doesn’t arrive within 3 minutes, check your spam folder.

Ok, Thanks

Read More