Weekly Construction Update: July 17
Road Closure: 88th Avenue
WHAT: Road closure
WHEN: Beginning July 20
WHERE: 88th Avenue, Quincy Street to New Holland Street, Zeeland Township
WHY: Culvert replacement
BACKGROUND: On Monday, July 20, the Ottawa County Road Commission will be closing 88th Avenue between Quincy Street and New Holland Street in Zeeland Township for a culvert replacement project.
This project is expected to last through July 31. Please note that all work is weather dependent and completion times are subject to change.
TRAFFIC IMPACT: A detour route will consist of Quincy Street to 96th Avenue to New Holland Street.
136th Avenue
WHAT: Permitted road closure
WHEN: Beginning July 20
WHERE: 136th Avenue, Port Sheldon Street to New Holland Street, Olive Township
WHY: Water transmission line installation
BACKGROUND: 136th Avenue between Port Sheldon Street and New Holland Street in Olive Township will be closed beginning July 20, 2026, for the installation of a City of Wyoming water transmission line.
This closure should last through August 7, 2026. Please note that all dates are tentative, and work is weather dependent.
More information about this project can be found here: City of Wyoming - Third Transmission Main - Prein&Newhof.
TRAFFIC IMPACT: The detour route is Port Sheldon Street to 144th Avenue to New Holland Street.
Tyler Street
WHAT: Road closure
WHEN: Beginning July 20
WHERE: Tyler Street, 96th Avenue to 104th Avenue, Olive Township
WHY: Culvert replacement
BACKGROUND: On Monday, July 20, the Ottawa County Road Commission will be closing Tyler Street between 96th Avenue and 104th Avenue in Olive Township for a culvert replacement project.
This work is expected to last through July 24. Please note that all work is weather dependent and completion times are subject to change.
TRAFFIC IMPACT: As this is a gravel road, there will be no posted detour route.
Beeline Road
WHAT: Road closure
WHEN: Beginning July 22
WHERE: Beeline Road, Greenly Street to cul-de-sac, Holland Township
WHY: Culvert replacement
BACKGROUND: On Wednesday, July 22, the Ottawa County Road Commission will be closing Beeline Road north of Greenly Street in Holland Township for a culvert replacement project.
This work is expected to last through July 24. Please note that all work is weather dependent and completion times are subject to change.
TRAFFIC IMPACT: As this is a dead-end road, there will be no posted detour route.
Current Projects & Closures
TOWNSHIP | ROAD | SEGMENT | WORK | DATES | AUTHORITY | TRAFFIC |
Holland | Beeline Rd. | Greenly St. to cul-de-sac | Culvert Replacement | July 22-24 | OCRC | Road Closed |
Zeeland | 88th Ave. | Quincy St. to New Holland St. | Culvert Replacement | July 20-31 | OCRC | Road Closed |
Olive | Tyler St. | 96th Ave. to 104th Ave. | Culvert Replacement | July 20-24 | OCRC | Road Closed |
Olive | 136th Ave. | Port Sheldon St. to New Holland St. | Water Main | July 20-Aug. 7 | Permit | Road Closed |
Olive/Robinson | 120th Ave. | M-45 to Taylor St. | Resurfacing | July 13-31 | OCRC | Lane Closures |
Park | 160th Ave. | S. Shore Dr. to W. 32nd Ave. | Resurfacing | July 13-24 | OCRC | Lane Closures |
Crockery | Cleveland St. | M-104 to 96th Ave. | Resurfacing | July 7-31 | OCRC | Lane Closures |
Spring Lake | Leonard St. | Spring Lake Village to 148th Ave. | Resurfacing | July 7-31 | OCRC | Lane Closures |
Holland | 104th Ave. | James St. to Felch St. | Bridge Rehab | July 6-Nov.30 | OCRC | Road Closed |
Grand Haven/Robinson | Lincoln St. | At 144th Ave. | Roundabout | July 6-Aug. 10 | OCRC | Road Closed |
Tallmadge | Linden Dr. | M-45 to Leonard St. | Culvert Replacement/ | July 6-TBD | OCRC | Road Closed |
Grand Haven | Ferris St. | 160th Ave. to 168th Ave. | Water Main/Pathway | June 8-Aug. 15 | Permit | Road Closed |
Allendale | 60th Ave | Lincoln St. to Comfort Dr. | Water Main | June 3-July 31 | Permit | Road Closed |
Olive | Port Sheldon St. | At 120th Ave. | Roundabout | June 1-Aug. 7 | OCRC | Road Closed |
Georgetown | 12th Ave. | Port Sheldon St. to Chicago Dr. | Bridge Rehabilitation | May 26-August 31 | OCRC | Road Closed |
Holland | Howard Ave. | Jefferson St. to N. River Ave. | Inspection | May 11-July 24 | Permit | Road Closed |
Olive | Van Buren St. | 144th Ave. to 136th Ave. | Water Main | May 4-Aug. 29 | Permit | Road Closed |
Holland | Lakewood Blvd. | 120th Ave. to U.S. 31 | Sanitary Sewer | May 4-Nov. 15 | Permit | Road Closed |
Jamestown | Adams St. | 40th Ave. to 36th Ave. | Bridge Rehabilitation | April 22-Nov. 6 | OCRC | Road Closed |
Holland | 124th Ave. | Ransom St. to New Holland St. | Road Reconstruction | April 13-July 24 | Permit | Road Closed |
Georgetown | 12th Ave. | Jackson St. North to End | Reconstruct | April 2-TBD | OCRC | Road Closed |
Georgetown | 48th Ave. | Port Sheldon St. to Baldwin St. | Water Main | March 30-Aug. 30 | Permit | Road Closed |
Olive | New Holland St. | 96th Ave. to 104th Ave. | Water Main | Nov. 12-Aug. 1 | Permit | Road Closed |
Olive | Van Buren St. | U.S. 31 to 120th Ave. | Water Main | Nov. 3-Sept. 1 | Permit | Road Closed |
Port Sheldon | Van Buren St. | Butternut Dr. to 144th Ave. | Water Main | Sept. 4-Aug. 1 | Permit | Road Closed |
Subdivision Resurfacing Schedule
TOWNSHIP | DATES |
Allendale | Beginning July 20 |
Jamestown | TBD |
Park | Beginning July 27 (est.) |
Information about township subdivision resurfacing projects can be found on the Township Subdivision Resurfacing project website.
— All dates listed in the above tables are estimates and are subject to change without notice. Always obey all work zone and road closure signs and be sure to follow all posted detours.