Road Closure: 48th Avenue

WHAT: Road closure

WHEN: Beginning June 22

WHERE: 48th Avenue, Garfield Street to Brucker Street, Polkton/Wright townships

WHY: Culvert replacement

BACKGROUND: On Monday, June 22, 48th Avenue between Garfield Street and Brucker Street in Polkton/Wright townships will be closed for a culvert-replacement project.

This closure is estimated to last through June 25; however, all work is weather-dependent and completion times are subject to change.

TRAFFIC IMPACT: A detour route will consist of Leonard Street to 68th Avenue to Garfield Street.

Road Resurfacing: 42nd Avenue

WHEN: Beginning June 22

WHERE: 42nd Avenue, Baldwin Street to Bauer Road, Georgetown Township

WHY: Road resurfacing

BACKGROUND: Tentatively beginning the week of June 22, contractors for the Ottawa County Road Commission are expected to begin work on a resurfacing project on 42nd Avenue between Baldwin Street and Bauer Road in Georgetown Township.

Work on this project is expected to last through July 10. Please note that all work is weather-dependent, and completion dates are subject to change.

TRAFFIC IMPACT: Traffic will be maintained using temporary lane closures under flag control during work hours. Be prepared for possible delays when traveling through this area while work is taking place.

Road Closure: Tyler Street

WHAT: Permitted closure

WHEN: Beginning June 22

WHERE: Tyler Street, 48th Avenue to 56th Avenue, Blendon Township

WHY: Water main work

BACKGROUND: Beginning June 22, Tyler Street between 48th Avenue and 56th Avenue in Blendon Township is expected to be closed for permitted water main work.

Work on this project is expected to last through June 27; however, all work is weather-dependent, and completion dates are subject to change.

TRAFFIC IMPACT: A detour route will utilize 56th Avenue.

Current Projects & Closures

TOWNSHIP

ROAD

SEGMENT

WORK

DATES

AUTHORITY

TRAFFIC

Blendon

Tyler St.

48th Ave. to 56th Ave.

Water Main

June 22-27

Permit

Road Closed

Polkton/
Wright

48th Ave.

Garfield St.to Brucker St.

Culvert Replacement

June 22-25

OCRC

Road Closed

Georgetown

42nd Ave.

Baldwin St. to Bauer Rd.

Resurfacing

June 19-July 10

OCRC

Lane Closure

Wright

Hayes St.

16th Ave. to Ironwood Dr.

Resurfacing

June 19-TBD

OCRC

Lane Closure

Grand Haven

Ferris St.

U.S. 31 to Lakeshore Dr.

Resurfacing

June 19-TBD

OCRC

Lane Closure

Robinson

120th Ave.

M-45 to Lincoln St.

Resurfacing

June 15-July 2

OCRC

Lane Closure

Grand Haven

Ferris St.

160th Ave. to 168th Ave.

Water Main/Pathway

June 8-Aug. 15

Permit

Road Closed

Allendale

60th Ave

Lincoln St. to Comfort Dr.

Water Main

June 3-July 31

Permit

Road Closed

Allendale

Warner St.

68th Ave. to 60th Ave.

Water Main

June 1-July 31

Permit

Road Closed

Olive

Port Sheldon St.

At 120th Ave.

Roundabout

June 1-July 10

OCRC

Road Closed

Georgetown

12th Ave.

Port Sheldon St. to Chicago Dr.

Bridge Rehabilitation

May 26-August 31

OCRC

Road Closed

Wright

Arthur St.

48th Ave. to 8th Ave.

Resurfacing

May 21-July 2

OCRC

Lane Closure

Allendale

56th Ave.

Lake Michigan Dr. to Alger St.

Road Work

May 11-July 4

Permit

Road Closed

Holland

Howard Ave.

Jefferson St. to N. River Ave.

Inspection

May 11-June 30

Permit

Road Closed

Olive

Van Buren St.

144th Ave. to 136th Ave.

Water Main

May 4-July 4

Permit

Road Closed

Holland

Lakewood Blvd.

120th Ave. to U.S. 31

Sanitary Sewer

May 4-Nov. 15

Permit

Road Closed

Jamestown

Adams St.

40th Ave. to 36th Ave.

Bridge Rehabilitation

April 22-Nov. 6

OCRC

Road Closed

Holland

124th Ave.

Ransom St. to New Holland St.

Road Reconstruction

April 13-July 3

Permit

Road Closed

Georgetown

12th Ave.

Jackson St. North to End

Reconstruct

April 2-TBD

OCRC

Road Closed

Georgetown

48th Ave.

Port Sheldon St. to Baldwin St.

Water Main

March 30-Aug. 30

Permit

Road Closed

Crockery

Cleveland St.

112th Ave. to 96th Ave.

Bridge Replacement

March 30-Oct. 2

OCRC

Road Closed

Allendale

Pierce St.

52nd Ave. to 56th Ave.

Road Work

March 9-July 4

Permit

Road Closed

Olive

New Holland St.

96th Ave. to 104th Ave.

Water Main

Nov. 12-June 19

Permit

Road Closed

Olive

Van Buren St.

U.S. 31 to 120th Ave.

Water Main

Nov. 3-Sept. 1

Permit

Road Closed

Port Sheldon

Van Buren St.

Butternut Dr. to 144th Ave.

Water Main

Sept. 4-Aug. 1

Permit

Road Closed

Subdivision Resurfacing Schedule

TOWNSHIP

DATES

Allendale

Beginning July 20 (est.)

Grand Haven

Beginning May 26

Jamestown

TBD

Park

Beginning July 27 (est.)

Spring Lake

Beginning June 18

Zeeland

Beginning June 17 (est.)

Information about township subdivision resurfacing projects can be found on the Township Subdivision Resurfacing project website. 

— All dates listed in the above tables are estimates and are subject to change without notice. Always obey all work zone and road closure signs and be sure to follow all posted detours.

ONN Staff profile image
by ONN Staff

Subscribe to Our Newsletter for Daily or Weekly Updates

Customize your email newsletter subscription for daily or weekly updates on your favorite topics.

Success! Now Check Your Email

To complete Subscribe, click the confirmation link in your inbox. If it doesn’t arrive within 3 minutes, check your spam folder.

Ok, Thanks

Read More