Weekly Construction Update: June 5
Ferris Street
WHAT: Permitted road closure
DURATION: June 8-Aug. 15
WHERE: Ferris Street, 168th Avenue to 160th Avenue, Grand Haven Township
WHY: Water main/Non-motorized pathway construction
BACKGROUND: On Monday, June 8, Ferris Street from 160th Avenue to 168th Avenue in Grand Haven Township will be closed for permitted water main and non-motorized pathway construction work.
This closure is estimated to last through Aug. 15; however, all work is weather-dependent and completion times are subject to change.
TRAFFIC IMPACT: A detour route will consist of U.S. 31 to Lincoln Street to 152nd Avenue.
Current Projects & Closures
TOWNSHIP | ROAD | SEGMENT | WORK | DATES | AUTHORITY | TRAFFIC |
Grand Haven | Ferris St. | 160th Ave. to 168th Ave. | Water Main/Pathway | June 8-Aug. 15 | Permit | Road Closed |
Allendale | 60th Ave | Lincoln St. to Comfort Dr. | Water Main | June 3-July 31 | Permit | Road Closed |
Georgetown | Parsons St. | 14th Ave. to 8th Ave. | Resurfacing | June 1-TBD | OCRC | Lane Closure |
Allendale | Warner St. | 68th Ave. to 60th Ave. | Water Main | June 1-8 | Permit | Road Closed |
Olive | Port Sheldon St. | At 120th Ave. | Roundabout | June 1-July 10 | OCRC | Road Closed |
Port Sheldon | 160th Ave. | At Van Buren St. | Water Main | May 27-June 10 | Permit | Road Closed |
Georgetown | 12th Ave. | Port Sheldon St. to Chicago Dr. | Bridge Rehabilitation | May 26-August 31 | OCRC | Road Closed |
Wright | Arthur St. | 48th Ave. to 8th Ave. | Resurfacing | May 21-July 2 | OCRC | Lane Closure |
Chester | 8th Ave. | Hoover St. to Gooding St. | Washout | Jan. 9-TBD | OCRC | Road Closed |
Park | 160th Ave. | Ottawa Beach Rd. to New Holland St. | Resurfacing | May 18-June 12 | OCRC | Lane Closure |
Allendale | 56th Ave. | Lake Michigan Dr. to Alger St. | Road Work | May 11-June 12 | Permit | Road Closed |
Holland | Howard Ave. | Jefferson St. to N. River Ave. | Inspection | May 11-June 12 | Permit | Road Closed |
Olive | Van Buren St. | 144th Ave. to 136th Ave. | Water Main | May 4-July 4 | Permit | Road Closed |
Holland | Lakewood Blvd. | 120th Ave. to U.S. 31 | Sanitary Sewer | May 4-Nov. 15 | Permit | Road Closed |
Jamestown | Adams St. | 40th Ave. to 36th Ave. | Bridge Rehabilitation | April 22-Nov. 6 | OCRC | Road Closed |
Holland | 124th Ave. | Ransom St. to New Holland St. | Road Reconstruction | April 13-July 3 | Permit | Road Closed |
Georgetown | 12th Ave. | Jackson St. North to End | Reconstruct | April 2-June 12 | OCRC | Road Closed |
Georgetown | 48th Ave. | Port Sheldon St. to Tyler St. | Water Main | March 30-Aug. 30 | Permit | Road Closed |
Crockery | Cleveland St. | 112th Ave. to 96th Ave. | Bridge Replacement | March 30-Oct. 2 | OCRC | Road Closed |
Allendale | Pierce St. | 52nd Ave. to 56th Ave. | Road Work | March 9-June 12 | Permit | Road Closed |
Olive | New Holland St. | 96th Ave. to 104th Ave. | Water Main | Nov. 12-June 10 | Permit | Road Closed |
Olive | Van Buren St. | U.S. 31 to 120th Ave. | Water Main | Nov. 3-June 6 | Permit | Road Closed |
Port Sheldon | Van Buren St. | Butternut Dr. to 144th Ave. | Water Main | Sept. 4-June 10 | Permit | Road Closed |
Subdivison Resurfacing Schedule
TOWNSHIP | DATES |
Allendale | Beginning July 20 (est.) |
Grand Haven | Beginning May 26 |
Jamestown | TBD |
Park | Beginning July 27 (est.) |
Spring Lake | Beginning June 22 (est.) |
Zeeland | Beginning June 17 (est.) |
Information about township subdivision resurfacing projects can be found on the Township Subdivision Resurfacing project website.
— All dates listed in the above tables are estimates and are subject to change without notice. Always obey all work zone and road closure signs and be sure to follow all posted detours.