Weekly Construction Update: Oct. 5
Photo by Zac Gudakov / Unsplash

Weekly Construction Update: Oct. 5

ONN Staff profile image
by ONN Staff

Road Resurfacing: Baldwin Street, 56th Avenue to 48th Avenue

WHEN: Beginning the week of Oct. 5

WHERE: Baldwin Street, 56th Avenue to 48th Avenue, Blendon Township

WHY: Road resurfacing

BACKGROUND: Beginning the week of Oct. 5, contractors for the Ottawa County Road Commission are expected to begin work on a resurfacing project on Baldwin Street from 56th Avenue to 48th Avenue in Blendon Township.

Work on this project is expected to last through late October; however, please note that all work is weather-dependent, and completion dates are subject to change.

Road Resurfacing: New Holland Street, Chicago Drive to Hudsonville City Limits

WHEN: Beginning the week of Oct. 5

WHERE: New Holland Street, Chicago Drive to Hudsonville City Limits

WHY: Road resurfacing

BACKGROUND: Beginning the week of Oct. 5, contractors for the Ottawa County Road Commission are expected to begin work on a resurfacing project on New Holland Street from Chicago Drive to the Hudsonville City Limits.

Work on this project is expected to last through mid-October; however, please note that all work is weather-dependent, and completion dates are subject to change.

TRAFFIC IMPACT: Traffic will be maintained using temporary lane closures under flag control. Be prepared for possible delays when traveling through this area while work is taking place.

Current Projects & Closures

TOWNSHIP

ROAD

SEGMENT

WORK

DATES

AUTHORITY

TRAFFIC

Blendon

Baldwin St.

56th Ave. to 48th Ave.

Resurfacing

Oct. 5-17

OCRC

Road Closed

Georgetown/
Jamestown

New Holland St.

Chicago Dr. to Hudsonville City Limits

Resurfacing

Oct. 2-23

OCRC

Lane Closures

Georgetown

Baldwin St.

20th Ave. to Cottonwood Dr.

Resurfacing

Sept. 28-Oct. 30

OCRC

Lane Closures

Holland

Beeline/Greenly St.

Riley St. to 120th Ave.

Resurfacing

Sept. 28-Oct. 16

OCRC

Lane Closures

Holland

James St.

At 120th Ave.

Sanitary Sewer

Sept. 21-Nov. 30

Permit 

Road Closed

Olive

120th Ave.

At Van Buren St.

Water Main

Sept. 14-30

Permit

Road Closed

Georgetown

28th Ave.

Hudsonville City Limits to Bauer Rd.

Resurfacing

Aug. 24-Oct. 5

OCRC

Lane Closures

Port Sheldon

164th Ave.

Butternut Dr. to New Holland St.

Water Main

Aug. 10-Nov. 30

Permit

Road Closed

Blendon/
Georgetown

48th Ave.

At Baldwin St.

Roundabout

July 27-Oct. 17

OCRC

Road Closed

Holland

104th Ave.

James St. to Felch St.

Bridge Rehab

July 6-Nov. 30

OCRC

Road Closed

Allendale

60th Ave

Lincoln St. to Comfort Dr.

Water Main

June 3-Oct. 30

Permit

Road Closed

Holland

120th Ave.

James St. to Lakewood Blvd.

Sanitary Sewer

May 4-Nov. 30

Permit

Road Closed

Georgetown

48th Ave.

Port Sheldon St. to Bauer Rd.

Water Main

March 30-Nov. 30

Permit

Road Closed

Olive

Van Buren St.

U.S. 31 to 120th Ave.

Water Main

Nov. 3-Nov. 30

Permit

Road Closed

Port Sheldon

Van Buren St.

Butternut Dr. to U.S. 31

Water Main

Sept. 4-Nov. 30

Permit

Road Closed

Subdivision Resurfacing Schedule

TOWNSHIP

DATES

Crockery

Beginning October 12

Jamestown

TBD

Park

Beginning August 24

Information about Township subdivision resurfacing projects can be found on the Township Subdivision Resurfacing project website. 

— All dates listed in the above tables are estimates and are subject to change without notice. Always obey all work zone and road closure signs and be sure to follow all posted detours.

ONN Staff profile image
by ONN Staff

Subscribe to Our Newsletter for Daily or Weekly Updates

Customize your email newsletter subscription for daily or weekly updates on your favorite topics.

Success! Now Check Your Email

To complete Subscribe, click the confirmation link in your inbox. If it doesn’t arrive within 3 minutes, check your spam folder.

Ok, Thanks

Read More