Weekly Construction Update: Sept. 18
Photo by Zac Gudakov / Unsplash

Weekly Construction Update: Sept. 18

ONN Staff profile image
by ONN Staff

James Street at 120th Avenue, Holland Township, begins Sept. 21

WHAT: Permitted road closure

WHEN: Beginning Sept. 21

WHERE: James Street at 120th Avenue, Holland Township

WHY: Sanitary sewer improvements

BACKGROUND: James Street at 120th Avenue in Holland Township will be closed beginning Monday, Sept. 21, for permitted sanitary sewer improvements.

This work is scheduled to last through late November. All dates are tentative, and work is weather-dependent.

For more information about this work, please visit the Holland Charter Township - Lakewood Blvd & 120th Ave Sewer Improvement Project information web page.

TRAFFIC IMPACT:

Local traffic will have access as follows:

  • 120th Ave from Lakewood to James will have access from the south via Lakewood Boulevard. 120th Avenue from Lakewood to James will continue to have one northbound lane open from Lakewood Boulevard to Garden Avenue. Local traffic will enter 120th from the south at Lakewood Boulevard, head north on 120th and exit via Garden Avenue back to Lakewood Boulevard. Local traffic south of the James and 120th intersection and north of Garden Avenue will have access north of Garden Avenue with two-way traffic to enter. The two-way traffic zone will also be redirected to Garden Avenue when exiting.
  • 120th Avenue from Riley to James will have access from the north via Riley/Felch.
  • James Street from US-31 to 120th will have access from the west via US-31.
  • James Street from 112th to 120th will have access from the east via 112th.

Current Projects & Closures

TOWNSHIP

ROAD

SEGMENT

WORK

DATES

AUTHORITY

TRAFFIC

Holland

James St.

At 120th Ave.

Sanitary Sewer

Sept. 21-Nov. 30

Permit 

Road Closed

Georgetown

Port Sheldon St.

12th Ave. to 8th Ave.

Sanitary Sewer

Sept. 17-25

Permit

Road Closed

Zeeland

64th Ave.

Perry St. to Byron Rd.

Culvert Replacement

Sept. 17-24

OCRC

Road Closed

Olive

120th Ave.

At Van Buren St.

Water Main

Sept. 14-30

Permit

Road Closed

Jamestown

24th Ave.

Perry St. to Byron Rd.

Culvert Replacement

Sept. 14-25

OCRC

Road Closed

Holland

Butternut Dr.

Lakewood Blvd. to Riley St.

Resurfacing

Aug.24-Oct.

OCRC

Lane Closures

Georgetown

28th Ave.

Hudsonville City Limits to Bauer Rd.

Resurfacing

Aug. 24-Oct.

OCRC

Lane Closures

Port Sheldon

164th Ave.

Butternut Dr. to New Holland St.

Water Main

Aug. 10-Nov. 30

Permit

Road Closed

Blendon/
Georgetown

48th Ave.

At Baldwin St.

Roundabout

July 27-Oct. 17

OCRC

Road Closed

Holland

104th Ave.

James St. to Felch St.

Bridge Rehab

July 6-Nov. 30

OCRC

Road Closed

Allendale

60th Ave

Lincoln St. to Comfort Dr.

Water Main

June 3-Sept. 19

Permit

Road Closed

Holland

120th Ave.

James St. to Lakewood Blvd.

Sanitary Sewer

May 4-Nov. 30

Permit

Road Closed

Georgetown

48th Ave.

Port Sheldon St. to Bauer Rd.

Water Main

March 30-Nov. 30

Permit

Road Closed

Olive

Van Buren St.

U.S. 31 to 120th Ave.

Water Main

Nov. 3-Nov. 30

Permit

Road Closed

Port Sheldon

Van Buren St.

Butternut Dr. to U.S. 31

Water Main

Sept. 4-Nov. 30

Permit

Road Closed

Subdivision Resurfacing Schedule

TOWNSHIP

DATES

Jamestown

TBD

Park

Beginning August 24

Information about Township subdivision resurfacing projects can be found on the Township Subdivision Resurfacing project website. 

— All dates listed in the above tables are estimates and are subject to change without notice. Always obey all work zone and road closure signs and be sure to follow all posted detours.

ONN Staff profile image
by ONN Staff

Subscribe to Our Newsletter for Daily or Weekly Updates

Customize your email newsletter subscription for daily or weekly updates on your favorite topics.

Success! Now Check Your Email

To complete Subscribe, click the confirmation link in your inbox. If it doesn’t arrive within 3 minutes, check your spam folder.

Ok, Thanks

Read More